Water-bomecoating engineering inspection batch mass acceptance record form

Water-based paint finishing project inspection batch quality acceptance record form




Water-based paint finishing project inspection batch quality acceptance record form 
GB50210-2001

030801
Unit (subunit) project name
Division (subdivision) project name
Acceptance site
Construction unit
project manager
Subcontractor
Subcontract Project Manager
Construction implementation standard name and number
Regulations on Construction Quality Acceptance SpecificationsConstruction unit inspection and evaluation recordsAcceptance records of supervision (construction) unit

master   project
 
1material qualityArticle 10.2.2

2Finishing Colors and PatternsArticle 10.2.3
3Comprehensive quality of finishingArticle 10.2.4
4Grassroots treatmentArticle 10.2.5

 
General   items
 
 
 
1Connection with other materials and equipmentArticle 10.2.9

2Thin paint finish quality allowable deviationcolorOrdinary finishingUniform
Advanced FinishingUniform
pan-alkaline, biting colorOrdinary finishingAllow a small amount of slight
Advanced Finishingnot allowed
flow, pimpleOrdinary finishingAllow a small amount of slight
Advanced Finishingnot allowed
Trachoma, brush patternOrdinary finishingA small amount of fine trachoma is allowed, and the brush pattern is smooth
Advanced FinishingNo blisters, no brush lines
Straightness of decorative line and color separation lineOrdinary finishing2
Advanced Finishing1
3Thick paint finishing quality allowable deviationcolorOrdinary finishingUniform
Advanced FinishingUniform
pan-alkaline, biting colorOrdinary finishingAllow a small amount of slight
Advanced Finishingnot allowed
point distributionOrdinary finishing——
Advanced Finishinguniform density
4Multiple coating quality tolerancecolorUniform
pan-alkaline, biting colornot allowed
Spray densityUniform, no contiguous pieces
Construction unit inspection and evaluation resultsProfessional Foreman (Construction Worker)
Construction team leader

Project Professional Quality Inspector:
       year month day
Acceptance conclusion of supervision (construction) unit
Professional Supervision Engineer 
(Professional technical person in charge of the project of the construction unit):

       year month day
Relevant knowledge