1. Formula with power-down protection function
2. Acceleration adjustable
3. With anti-fly protection and alarm
4. With anti-glue protection and alarm
5. With automatic reminder function
After the installation and general connection of the mechanical pump and glue homogenizer are completed, the glue homogenization operation can be carried out. The specific steps are as follows:
1. Turn on the power: turn on the power switch of the glue homogenizer and the oil-free pump in turn;
2. Recipe setting: Click the recipe button to perform related operations of the recipe. For details of the operation method, see Figure 6 and its description;
3. Other settings:
Set the pre-suction time, desorption time and air pressure detection status according to your own needs; the pre-suction time and desorption time are default
0s, the air pressure detection switch is on by default (recommended to be on), see Figure 8 and description for the operation method;
4. Play the film
Place the substrate to be evenly glued on the sheet holder (see Figure 12);
5. Suction tablet: press the button of taking tablet/suction tablet to complete the suction tablet;
6. Epoxy:
· Static Epoxy
If glue dispensing is to be performed in a static state, this operation should be completed between steps 5 and 6.
· Low speed dispensing
If glue dispensing is required at low speed, the corresponding low speed section should be set in step 2, and the operation should be completed when the motor .
7. Start: Press the start/stop button, the motor starts and runs according to the parameter setting requirements, if step 5 is not operated, this step will automatically suck the film;
8. Take the film:
· Process taking
If you need to take and put the film in the process of uniform glue, you should press the pause/resume button. After the motor pauses, press the take/suction button to take and put the film.
· Terminate fetching
a. You can press the start/stop button to forcibly end a gluing process. After the motor stops running, perform pick-and-place and slice operations, and repeat steps 4 and 5 for pick-and-place operations.
b. After a glue homogenization process is automatically ended, after the prompt interface for taking the film pops up (see Figure 11), perform the operation of taking and putting the film, and repeat steps 4 and 5 for the taking and putting operation.